Work schedule planning.

13/10/2016

0 Comments

 
Around 13 weeks for negotiated 1
Around 17 weeks, closer to 15 for negotiated 2
Asset list:
  • Door+door-frame | 1 hour | Complete
  • Shop window | 2 hours | Complete
  • Large window | Complete
  • Small window | Complete
  • Roof | Complete
  • Attic window extension | Complete
  • Brick groups | Complete
  • Drainpipe parts (short,long,curved) | Complete
  • Floor tiles (At least 3) | Complete
  • Pavement | Decided not neccesary
  • Bin | Complete
  • Lamppost | Complete
  • Bench | Complete
  • Planter | Complete
  • Newspaper | Complete
  • Construction barriers | Complete
  • Bin bag | Complete
  • Character (Foot, Leg, Torso, Arm, Head, Hand)

Roughly 4 weeks to model everything listed if only including lesson time, around 2 if including lesson times and at least 4 hours of work each day for the rest of the week.

Potential assets if time allows:
  • Tree
  • Garden floor tile
  • Fence
  • Grass
  • Bushes (3 variants)
UV unwrapping the models will be the time consuming part. It is difficult to say how long I think each part will take but I'll make a guess to get a rough time frame.
  • Door and frame = 3 | Complete
  • Shop window = 4 | Complete
  • Large window = 3 | Complete
  • Small window = 3 | Complete
  • Roof = 3 | Complete
  • Attic window = 4 | Complete
  • Bricks = 1 | Complete
  • Drainpipe parts = 3 | Complete
  • Floor = 1 | Complete
  • Pavement = 2 | Complete
  • Bench = 4 | Complete
  • Planter = 5 | Complete
  • Newspaper = >1 | Complete
  • Construction Barriers = 4 | Complete
  • Bin bag = 2
  • Character = 12
Texture list
  • Door+door-frame (4 variants)
  • Shop window (4 variants)
  • Large and Small window (2 variants)
  • Roof (3 variants)
  • Brick groups (2 variants)
  • Drainpipe
  • Floor and pavement (3 variants)
  • Bin
  • Lamppost
  • Bench (2 variants)
  • Planter
  • Newspaper (2 variants)
  • Construction barriers
  • Bin bag

If I am able to use downloaded textures and the software 'Substance Painter' then the texturing of these objects should not cause much of a problem and only take 2 weeks maximum. If I am required to make all of the textures myself then I may have to sacrifice a lot of the variation and quality for the sake of not spending too much of my time on the task.

Potential textures if time allows:
  • Tree
  • Grass floor
  • Fence (2 variants)
  • Grass
  • Bushes (2 variants)
It could take some time to rig the character if I need to do it without any software help, however I believe I can use Maya 2016 to auto-rig a character and there are other website alternatives such as Mixamo. If I can use these then I estimate maybe 2-3 hours to rig my character. If I cannot my guess would be around 15 hours.
0 Comments



Leave a Reply.

    Picture

    Author

    This is where I will be posting all of my work updates. 
    -Herbie Southern

    Archives

    October 2022
    September 2022
    May 2022
    April 2022
    September 2018
    September 2017
    May 2017
    March 2017
    February 2017
    November 2016
    October 2016
    July 2016
    June 2016

    Categories

    All
    Contextual Studies 3
    Creative Futures 3
    Misc. Updates
    Negotiated Studies 1
    Negotiated Studies 2

Home

Animation

Blog

Contact

Copyright © 2015
  • Portfolio
  • More
    • Animation >
      • BTM Onboarding Animations
    • Coding
    • Asset Creation
  • Blog
  • Contact